operation management 需要过程(急),You’ve just completed a pilot run of 10 units of a major product and found the processing timefor each unit was as follows:UNIT NUMBER TIME (HOURS)1 9702 6403 4204 3805 3206 2507 2208 2079 19010 190a.Accor

来源:学生作业帮助网 编辑:作业帮 时间:2024/04/27 17:38:50
operation management 需要过程(急),You’ve just completed a pilot run of 10 units of a major product and found the processing timefor each unit was as follows:UNIT NUMBER TIME (HOURS)1 9702 6403 4204 3805 3206 2507 2208 2079 19010 190a.Accor

operation management 需要过程(急),You’ve just completed a pilot run of 10 units of a major product and found the processing timefor each unit was as follows:UNIT NUMBER TIME (HOURS)1 9702 6403 4204 3805 3206 2507 2208 2079 19010 190a.Accor
operation management 需要过程(急),
You’ve just completed a pilot run of 10 units of a major product and found the processing time
for each unit was as follows:
UNIT NUMBER TIME (HOURS)
1 970
2 640
3 420
4 380
5 320
6 250
7 220
8 207
9 190
10 190
a.According to the pilot run,what would you estimate the learning rate to be?
b.Based on a,how much time would it take for the next 190 units,assuming no loss of learning?
c.How much time would it take to make the 1,000th unit?

operation management 需要过程(急),You’ve just completed a pilot run of 10 units of a major product and found the processing timefor each unit was as follows:UNIT NUMBER TIME (HOURS)1 9702 6403 4204 3805 3206 2507 2208 2079 19010 190a.Accor